TXDOT to Rehab FM 121 East

TxDOT is doing a rehabilitation project for FM 121 that goes from the railroad tracks in Van Alstyne all the way to SH 160.  From the railroad tracks to Lincoln Park Road TxDOT will be milling off 2” of the surface and repaving it at the same elevation.  From Lincoln Park Road to SH 160 TxDOT will reclaim the roadway, add 8” of additional flexible base and add a two course surface treatment.  Because TxDOT will have traffic running on flexible base while the project in under construction, TxDOT plans to reduce the speed limit at the construction area where they are working and move it through the project.  TxDOT will post the area under construction to be 45 mph instead of the usual 55 mph.  The contractor will rehab the project in 2 mile segments to limit how much of the roadway is under raw base at a time. TxDOT will also replace cross drainage structures under the roadway and replace the signage along the road.  The project is already underway and is expected to be completed in January 2026.